The Draft Compensation Site Plan (CSP) and the Draft Mitigation Bank Instrument (MBI) were submitted to the US Army Corps of Engineers and to the Inter-agency Review Team for their review on May 16, 2016.

The Final Prospectus was submitted on September 1, 2015.  It was put out for public comment on November 9, 2015.  Public comment closed on December 9, 2015.  The Draft Compensation Site Plan (CSP) & Mitigation Bank Instrument (MBI) are being developed currently.

Members from the IRT made a site visit on June 22, 2015, after the submittal of the Draft Prospectus on June 8, 2015.  The IRT was represented by Sue Elston, US EPA, Pam Schense, WDNR, and Rebecca Graser, US ACOE.  Maria Scholze, Agent, and John Scholze, plant specialist, from Wisconsin Wetland Specialists were also on-site for the visit.  Emery Palmer, owner, High Cliff Consulting, was also present.

IRT FIRST VISIT_cropped_comp.jpg

On April 19 - 22, 2015, Wisconsin Wetland Specialists probed to locate and then mapped the location of the existing sub-surface drainage tile system on the site.  Initial site photos were taken, as well as, initial documentation of the early vegetation in preparation for the writing on the Prospectus.